Riot Platforms, Inc. (RIOT) filed an 8-K current report with the SEC on August 14, 2026 reporting Item 1.01 (Entry into a Material Definitive Agreement), Item 2.03 (Creation of a Direct Financial Obligation). $573.0 million delayed-draw senior secured facility for Rockdale’s 191 critical IT MW data center project.
Riot Platforms, Inc. 8-K event analysis
AI summary of each reported item and its exhibits
Item 1.01 · Entry into a Material Definitive Agreement
- $573.0 million delayed-draw senior secured facility for Rockdale’s 191 critical IT MW data center project
- Proceeds target long-lead equipment, project equipment and related expenses, supporting accelerated infrastructure deployment
- Interest: Adjusted Term SOFR plus 2.75% or Base Rate plus 1.75%, at borrower’s election
- Maturity December 31, 2026, creating a near-term refinancing or repayment requirement
- Collateral and guarantees limited to Credit Parties, with substantially all their assets pledged and no general parent recourse
Item 2.03 · Creation of a Direct Financial Obligation
- Item 2.03 contains no standalone borrowing terms, amounts, interest rates, maturity dates, or financing purpose
- Financial-obligation details are incorporated from Item 1.01, requiring review of that section for investor impact
Generated from the filing text and exhibits; verify against the original. What 8-K item codes mean
Other Riot Platforms, Inc. 8-K filings
Get the next RIOT 8-K as it lands