PORTLAND GENERAL ELECTRIC CO /OR/ (POR) filed an 8-K current report with the SEC on October 29, 2026 reporting Item EX-99.1 (Exhibit EX-99.1), Item EX-99.2 (Exhibit EX-99.2), Item 2.02 (Results of Operations and Financial Condition), Item 7.01 (Regulation FD Disclosure). Q3 and nine-month financial results announced for periods ended September 30, 2026.
PORTLAND GENERAL ELECTRIC CO /OR/ 8-K event analysis
AI summary of each reported item and its exhibits
Item 2.02 · Results of Operations and Financial Condition
- Q3 and nine-month financial results announced for periods ended September 30, 2026
- Investor-relevant figures and management commentary contained in Exhibit 99.1 press release
Item 7.01 · Regulation FD Disclosure
- October 29, 2026 quarterly earnings call and webcast scheduled for 11:00 a.m. ET
- Exhibit 99.2 slide presentation provides investor materials accompanying the earnings discussion
- Presentation may offer forward-looking detail on operating performance, capital plans and guidance
Item EX-99.1 · Exhibit EX-99.1
- Q3 adjusted EPS $1.06, up from $1.00, despite mild weather creating a $0.15 year-over-year headwind
- 2026 adjusted EPS guidance reduced to $3.18 to $3.28, with long-term outlook unchanged
- Industrial demand rose 9% weather-adjusted, led by high-tech and data center customers
- $1.565 billion 2026 capital spending plan, including approximately $900 million Biglow and $853 million Salmonfly projects
- EDAM participation expected to generate approximately $14 million in customer savings during 2027
Item EX-99.2 · Exhibit EX-99.2
- 2026 adjusted EPS guidance cut to $3.18-$3.28 from $3.33-$3.53, signaling near-term earnings pressure
- Q3 adjusted EPS $1.06, $0.20 below guidance midpoint, with unfavorable weather creating a $0.13 year-over-year headwind
- Weather-adjusted load-growth guidance reduced to 1.0%-2.0%, while long-term 3% load and 5%-7% EPS growth targets remain intact
- $7.4B capital forecast supports rate-base expansion, excluding approximately $1.75B for Biglow Optimization Phase 2 and Salmonfly
- Washington utility acquisition remains targeted for mid-2027 closing, subject to regulatory approvals and financing execution
Generated from the filing text and exhibits; verify against the original. What 8-K item codes mean