8-K current report · filed Oct 22, 2026

NET Power Inc. (NPWR) 8-K Current Report: October 22, 2026

Item 1.01NPWR overview

Short answer

NET Power Inc. (NPWR) filed an 8-K current report with the SEC on October 22, 2026 reporting Item 1.01 (Entry into a Material Definitive Agreement). FNTP and mobilization deadline extended from October 15, 2026 to March 31, 2027.

NET Power Inc. 8-K event analysis

AI summary of each reported item and its exhibits

Item 1.01 · Entry into a Material Definitive Agreement

  • FNTP and mobilization deadline extended from October 15, 2026 to March 31, 2027
  • Fourth Amendment and LNTP, plus required payments, must be completed by November 15, 2026
  • Failure by November 15 triggers $3.5 million termination payment within ten days of demand
  • Further failure by March 31, 2027 to deliver FNTP and fund mobilization also triggers $3.5 million payment
  • Extension preserves project negotiations but delays construction commitment and associated cash deployment

Generated from the filing text and exhibits; verify against the original. What 8-K item codes mean