8-K current report · filed Jul 29, 2026

Ramaco Resources, Inc. (METC) 8-K Current Report: July 29, 2026

Item EX-99.1Item EX-99.2Item EX-99.3Item 7.01METC overview

Short answer

Ramaco Resources, Inc. (METC) filed an 8-K current report with the SEC on July 29, 2026 reporting Item EX-99.1 (Exhibit EX-99.1), Item EX-99.2 (Exhibit EX-99.2), Item EX-99.3 (Exhibit EX-99.3), Item 7.01 (Regulation FD Disclosure). Hatch conceptual study released for Brook Mine rare earth and critical minerals project.

Ramaco Resources, Inc. 8-K event analysis

AI summary of each reported item and its exhibits

Item 7.01 · Regulation FD Disclosure

  • Hatch conceptual study released for Brook Mine rare earth and critical minerals project
  • Shareholder letter outlines Hatch findings and company internal projections
  • Investor materials posted online, including Hatch Report, shareholder letter, and Ramaco Research Rodeo video
  • Brook Mine development remains exploratory, with potential strategic diversification beyond metallurgical coal

Item EX-99.1 · Exhibit EX-99.1

  • Hatch Initial Assessment advances Brook Mine’s greenfield critical-minerals project using carbo-chlorination to recover gallium, germanium, scandium and rare earth elements
  • Base case processes 1.3 million dry metric tonnes annually at 92% availability, with 574 dry tonnes of CMO-equivalent output targeted
  • Byproduct targets include 11,848 tonnes of HPA and 18,617 tonnes of HPS annually, materially above the original 1,800-tonne HPA target
  • Economic confidence remains early-stage, with AACE Class 5 CAPEX accuracy of +30%/-50% and key process test work scheduled to begin September 2026
  • Project economics and design remain exposed to unresolved technology, permitting, infrastructure, waste-management and tailings requirements

Item EX-99.2 · Exhibit EX-99.2

  • Hatch conceptual study shifts Brook Mine to carbochlorination, with projected pre-tax NPV8 $8.0B and IRR 24%
  • Projected average annual EBITDA $1.3B and revenue $1.7B, based on Ramaco’s unverified internal model
  • Construction capital estimated at $3.2B plus $0.8B contingency, creating substantial future financing needs
  • Approximately 75% of projected revenue tied to semiconductor-linked gallium, germanium, HPA and HPS demand
  • Project remains exploration stage, relying on inferred resources and AACE Class 5 estimates with -35%/+50% accuracy; pilot operation targeted for later 2027

Item EX-99.3 · Exhibit EX-99.3

  • Hatch initial assessment evaluates refining process, preliminary flowsheet, capital costs and operating costs for Brook Mine critical minerals project
  • Study marks milestone toward Ramaco’s proposed integrated domestic critical minerals and rare earth platform
  • Brook Mine remains exploration stage, with commercial development and resource conversion still unproven
  • Project requires continued investment in rare earth capabilities, including pilot and potential full-scale processing facilities

Generated from the filing text and exhibits; verify against the original. What 8-K item codes mean