8-K current report · filed Nov 12, 2026

Fermi Inc (FRMI) 8-K Current Report: November 12, 2026

Item 2.02Item 7.01Item EX-99.1Item EX-99.2FRMI overview

Short answer

Fermi Inc (FRMI) filed an 8-K current report with the SEC on November 12, 2026 reporting Item 2.02 (Results of Operations and Financial Condition), Item 7.01 (Regulation FD Disclosure), Item EX-99.1 (Exhibit EX-99.1), Item EX-99.2 (Exhibit EX-99.2). Earnings release covers third quarter ended September 30, 2026.

Fermi Inc 8-K event analysis

AI summary of each reported item and its exhibits

Item 2.02 · Results of Operations and Financial Condition

  • Earnings release covers third quarter ended September 30, 2026
  • Conference call scheduled November 12, 2026 at 8:00 a.m. CT / 9:00 a.m. ET
  • Financial results and management commentary available in Exhibit 99.1

Item 7.01 · Regulation FD Disclosure

  • Investor presentation published November 12, 2026 on Fermi’s investor relations website
  • Exhibit 99.2 contains the substantive investor updates, potentially including strategy, operations and financial outlook
  • Regulation FD distribution makes the same information broadly available to investors

Item EX-99.1 · Exhibit EX-99.1

  • Investment-grade hyperscaler committed $200 million upfront for 600 MW at Project Matador, improving funding visibility but before a definitive lease
  • Additional $90 million materials agreement remains under finalization, creating potential customer-funded acceleration of data-center construction
  • TensorWave lease and AMD credit support terminated, removing a previously announced customer commitment from the development pipeline
  • Q3 net loss $141.6 million, or $0.22 per share, with $142.2 million of general and administrative expenses
  • Cash and restricted cash $315.5 million against $958.4 million debt, while nine-month capital investment reached $759.5 million

Item EX-99.2 · Exhibit EX-99.2

  • Q3 2026 loss $142M, or $0.22 per share, with $55M operating cash use and $133M PP&E investment
  • Liquidity includes $1.2B commitments, but $958M net debt and high-cost equipment financing increase funding risk
  • Project Matador targets 600 MW reserved for 2027 by a major hyperscaler, supporting early revenue conversion
  • Hillcore framework adds up to 2.6 GW without Fermi plant capital or debt, but requires contracted customer demand
  • Scale ambitions reach 17 GW, while additional capacity remains contingent on permits, financing, interconnection and tenant agreements

Generated from the filing text and exhibits; verify against the original. What 8-K item codes mean