Item 8.01 · Other Events
- NCUC approved DEC and DEP settlements, supporting revised customer rates effective January 1, 2027
- Approved 9.8% ROE based on a 53% equity capital structure
- Historic retail rate bases: $25.7B for DEC and $17.8B for DEP
- Two-year MYRP authorizes $3.8B DEC and $3.4B DEP North Carolina capital, with annual refund mechanism
- $10M pre-tax fourth-quarter 2026 charge for each utility, classified as special items and excluded from adjusted earnings
Item EX-99.1 · Exhibit EX-99.1
- NCUC approved DEC’s North Carolina rate settlement, producing $496 million of revenue requirement over two years and average annual increases of 3.7%
- Year 1 rates expected January 1, 2027, improving near-term revenue visibility for Duke Energy Carolinas
- Approved ROE 9.8% with 53% equity capitalization, below DEC’s revised 10.48% request
- MYRP includes $3.8 billion of North Carolina capital, with annual refunds tied to project completion and capital placed in service
- Data-center protections include 15-year contracts, 75% minimum billing demand, customer-funded facilities, and stranded-generation security charges
Item EX-99.2 · Exhibit EX-99.2
- NCUC approved DEP’s North Carolina settlement, setting a $338 million two-year revenue increase, below the revised $610 million request
- Approved 9.8% ROE and 53% equity component, supporting regulatory earnings but below DEP’s revised 10.48% request
- Two-year MYRP includes $3.4 billion of projected capital, with annual refunds if approved investment is not completed
- Data-center tariff adds 15-year contracts, 75% minimum billing demand, customer-funded facilities and stranded-generation protections
- Year 1 rates begin January 1, 2027; DEP expects a $10 million fourth-quarter 2026 pre-tax charge excluded from adjusted earnings
Generated from the filing text and exhibits; verify against the original. What 8-K item codes mean
Other Duke Energy 8-K filings
Get the next DUK 8-K as it lands
Follow DUK for push alerts, or ask the research agent what this filing means.